H2010, Leeds

H2010, Leeds

Client: DJR Smith / Miller Homes - H2010, Leeds

Project: Yarn Street-H2010

Value: £50,000.00

Duration: 52 weeks

Details: Smoke Control Systems worked closely the electrical contractor to help them achieve their completion dates on time for all phases of the in town waterside development for Miller Homes.

Each of the multi-occupancy apartment blocks was installed with multizone control panels to interface the fire alarm with a range of AOV windows and roof vents