Stafford Hospital

 

stafford_hospital

Client: Stafford Hospital

Project: Move dampers and modify pipe work to AOV to make way for new plant.

Value: £3000.00

Duration: 1 week

Details: Isolate, disconnect and make ready for damper to be moved by main contractor. Reconnect, and test once damper had been removed.