Old Bostik Warehouse, Stafford

bostik

Client: Onyx - Old Bostik Warehouse, Stafford

Project: Refurbishment to existing system

Value: £9,000.00

Duration: 4 Weeks

Details: After been left un-used for several years the Smoke Ventilation System at this warehouse needed extensive repairs and replacements including a new compressor, control valves and several new pneumatic actuators. The actuators had to be custom made to suit as the existing supplier was no longer in business.